Portugal's main electricity operator, EDP, has successfully restored power to all customers affected by the unprecedented storm sequence that battered the country from late January through February 2026 — a nearly month-long recovery operation that required 2,400 field personnel and international assistance from four countries.
Why This Matters:
• Full service restoration announced February 26, but the definitive grid reconstruction will take months and require €4.1B in infrastructure investment through 2030
• €80M in direct damage to EDP alone; total national economic losses from the storm convoy estimated at €5-6B across all sectors
• 6,000 km of electrical grid and 5,800 transmission towers suffered damage described as "unprecedented" by the utility's leadership
The Storm Convoy That Crippled Portugal's Grid
The electrical infrastructure damage stemmed from what meteorologists dubbed a "storm convoy" — five successive low-pressure systems (Ingrid, Joseph, Kristin, Leonardo, and Marta) that hammered Portugal with wind speeds exceeding 200 km/h. Monte Real recorded a peak gust of 178 km/h, comparable to the highest readings in the Portuguese Institute for Sea and Atmosphere's historical database.
At the crisis peak, nearly 1M residents lost power nationwide, with Storm Kristin alone leaving half a million people in darkness. The Centro, Lisbon and Tagus Valley, and Alentejo regions absorbed the most severe grid failures. E-Redes, EDP's distribution arm, faced what CEO Miguel Stilwell d'Andrade characterized as "physical damage without precedent" to the country's energy backbone.
Mobilizing a Four-Nation Emergency Response
The utility's restoration operation drew on a multinational coalition of line crews. Beyond Portugal's internal resources, EDP deployed technical teams from Spain, Brazil, France, and Ireland to tackle the sprawling repair challenge. Hydroelectric plant personnel worked continuously to limit storm-related damage while grid restoration proceeded.
By February 5, more than 80,000 customers still lacked electricity. Three weeks later, on February 22, approximately 1,800 connections remained offline. The company declined initially to commit to a fixed restoration deadline, citing the scale of structural damage.
On February 4, EDP suspended billing for 700,000 customers in the most affected zones and offered interest-free payment plans, a gesture costing the company over €800,000 in customer relief.
What This Means for Residents and Businesses
While EDP confirmed February 26 that 100% of standard service has been restored, Stilwell d'Andrade acknowledged "a few specific situations" still require resolution. More significantly, the company warned that permanent reconstruction of the damaged grid will extend for months beyond the provisional repairs that brought customers back online.
The broader economic toll eclipses the utility sector. Economy Minister Manuel Castro Almeida pegged direct reconstruction costs from Storm Kristin alone at €4B (€4.7B including indirect supply chain disruptions). Paulo Fernandes, who leads the government's Centro Region Reconstruction mission, estimated total losses across the storm series at €5-6B, factoring in public infrastructure, agro-forestry sectors, housing, and commercial enterprises.
The Portuguese Insurance Association reported more than 115,000 claims by mid-February, with insured losses exceeding €500M. Of this, €360M had been paid or reserved, split primarily between residential damage (€170M) and commercial/industrial facilities (€150M).
Tourism operators in the Norte and Centro regions reported 60% of Carnival bookings were affected, with 56% anticipating negative impacts extending into Easter reservations, according to the National Association of Travel Agencies.
Hydroelectric Windfall Amid Catastrophe
The same intense precipitation that toppled transmission towers filled Portugal's reservoirs to 96% capacity — up from 76% in January and nearing historic maximums. Hydroelectric output through mid-February doubled the historical average, Stilwell d'Andrade noted during EDP's 2025 earnings call.
This surplus water dumped wholesale electricity prices from approximately €71/MWh in January to just €8/MWh by mid-February, creating paradoxical market conditions where abundant renewable generation coincided with elevated costs for grid balancing services.
EDP deployed advanced hydrological modeling to anticipate reservoir discharges and coordinate with environmental authorities on flood control — a critical task as more than 50 national monuments sustained damage, with restoration pegged at €20M. Near the Mondego River, a breached dike caused partial collapse of an A1 motorway section, forcing evacuation of roughly 3,000 residents.
€4.1B Infrastructure Investment Through 2030
Stilwell d'Andrade framed the storm damage as evidence of "growing vulnerability" tied to climate change, reinforcing the necessity for more resilient energy systems. EDP plans to invest €4.1B in Iberian Peninsula grids between 2026 and 2030 — a 58% increase over the 2021-2025 period's €2.6B.
Portugal accounts for 66% of that increase in grid spending. More than €500M will target specific resilience upgrades, preparing the network for higher loads, distributed generation, and increased system complexity — particularly data center demand driving electrification across the Iberian Peninsula.
Currently, only 20% of Portugal's electrical distribution runs underground, compared to roughly 45% in Spain and Italy. Underground cabling resists storm damage but costs four to ten times more than overhead lines and complicates maintenance and repairs. Experts have called for European funding to accelerate Portugal's undergrounding program.
The new Portuguese regulatory framework sets a nominal pre-tax return of 6.7% through 2029, which EDP leadership described as providing "clarity and stability" for the investment cycle.
How Europe's Utilities Tackle Extreme Weather
EDP's storm response aligns with broader European utility strategies for climate resilience. Spain's Iberdrola invested €1.6B over three years in smart grid digitalization, enabling restoration of 65% of customers within three minutes and 80% within an hour following the 2019 DANA storm.
Key resilience measures across European operators include:
• Smart grid automation to isolate faults and reroute power faster
• Strategic vegetation management and drone-based line inspections using LIDAR technology
• Foundation and tower reinforcement to withstand higher wind loads
• Microgrids and battery storage that operate independently if transmission fails
• Elevation of substations above projected flood levels
The European Commission's REPowerEU plan prioritizes energy infrastructure resilience, and incentive-based regulation models are emerging to reward utilities that improve service quality and storm preparedness.
Government Mobilizes €2.5B Recovery Package
The Portuguese Cabinet approved a €2.5B support package for citizens, businesses, and infrastructure recovery. This includes €400M for Infraestruturas de Portugal to repair roads and rail, €200M in municipal government aid, and €20M for cultural heritage restoration.
The storms caused six fatalities in Portugal and 13 total across Portugal, Spain, and Morocco, displacing hundreds. Portugal declared a state of calamity initially through February 15, extended in severely affected zones. Presidential elections were postponed in certain areas due to the crisis.
The Sistema Terrestre Sustentável Association (ZERO) cautioned that adding indirect losses and urgent preventive adaptation, Portugal's annual climate resilience costs could approach €6B in 2026.
Timeline: From Blackout to Full Restoration
• Late January: Storm convoy begins with Depression Ingrid
• Early February: Storm Kristin peaks; ~1M residents lose power
• February 4: EDP suspends billing for 700,000 customers
• February 5: 80,000+ customers still without electricity; E-Redes offers no firm restoration date
• February 22: Approximately 1,800 customers remain offline
• February 26: EDP announces 100% service restoration, with only isolated cases pending
Telecom operators Meo and Vodafone also announced bill credits for customers impacted by prolonged service interruptions, as the storms felled trees and caused landslides that severed fiber and cellular infrastructure.
Stilwell d'Andrade acknowledged the "frustration of people who were without electricity for these weeks" and pledged continued evaluation of storm impacts, with a full accounting expected in the first-quarter financial update.
The Portugal Post in as independent news source for english-speaking audiences.
Follow us here for more updates: https://x.com/theportugalpost
Portugal faces €4 billion storm damage. Homeowners can claim €10k repair grants, pause mortgages for 12 months, and firms tap €2 billion credit—apply before deadlines.
Portugal rolls out €2.5 billion Storm Kristin fund: grants, tax breaks, toll waivers and 12-month loan holidays. Power & telecom services due back by 10 Feb.
Portugal invests €400m in tougher cables, grid batteries and smart controls to avoid another power outage—good news for remote workers and homeowners.
Portugal's grid hardening, big battery storage and tax tweaks cut blackout risk while adding just 1¢ to a €25 bill. See what the 2025-28 plan means.