Gardunha’s rolling foothills, usually a quiet backdrop for cherry groves and hiking trails, have suddenly become the stage for Portugal’s loudest debate on renewable energy. At the heart of the dispute lies a single question: can the country meet its climate targets without sacrificing the very landscapes that make the interior worth living in?

Why Beira Baixa is at the centre of a new energy row

It took only a few weeks of public consultation for the planned Sophia photovoltaic complex to evolve from a technical file into a symbol. On one side stand municipal leaders, land-steward farmers and conservationists who see “1 737 hectares of fencing” as a threat to the fragile mosaic of granitic hills, cork oak patches and Natura 2000 corridors that define Fundão, Penamacor and Idanha-a-Nova. On the other side, project sponsor Lightsource bp points to 867 MWp of clean capacity, an annual output able to supply more than 370 000 homes and a capital injection of €590 million—all in a region struggling with depopulation.

The tension is sharpened by geography. Beira Baixa has stayed largely outside the solar gold-rush that transformed the Alentejo, preserving an agricultural and eco-tourism economy built on the Gardunha Range’s rain-shadow microclimate. Locals fear that carpeting valley floors with photovoltaic tables will erase the marketing edge won through years of rewilding, trail-building and low-impact tourism.

A €590 million proposal and a 1 737-hectare question mark

Sophia is no ordinary solar farm. Its environmental impact study acknowledges that 390 hectares will host panels, yet critics warn the remaining perimeter is equally transformative: service roads, trenches, drainage swales, security lighting and a new corridor of Very High Voltage lines. Rewilding Portugal’s analysis labels the plan “territorial artificialisation”, arguing that placing steel and glass over a living soil crust turns a carbon sink into an “ecological desert”.

Lightsource counters with compensatory planting. The company pledges to convert 135 hectares of eucalyptus into cork oak and holm oak woodland, plant around 27 000 native trees and restore riparian vegetation across 228 hectares. For corporate strategists, those numbers embody a model Portuguese policymakers have long encouraged: private renewables that also bankroll reforestation, drought resilience and rural jobs.

From promises of jobs to fears of ecological rupture

Economic sweeteners have not quelled suspicion in Penamacor’s town hall. Councillors highlight 1 000 construction-phase jobs that disappear once the array is built, leaving only a handful of maintenance posts. They contrast that with the possible loss of agritourism revenues, the cost of burying rural identity under acres of imported hardware, and the risk that solar glare or micro-climatic heat islands could harm nearby cherry orchards.

Environmental organisations, including Zero, Quercus and Fapas, go further. Their submissions to the Portuguese Environment Agency accuse the impact report of data gaps on migratory raptors, under-counted water tables and optimistic carbon accounting. They insist that a truly just transition would start by filling warehouse roofs, road verges and former quarries—spaces already stripped of ecological function—before touching intact habitats in inland districts that still harbour wolf dispersal routes, reptiles and steppe birds.

Transparency cloud: who decides and when

The process itself is fuelling anger. Opponents cite a “lack of clarity over ultimate ownership”, obscure special-purpose vehicles and last-minute document uploads during the six-week consultation that closed on 20 November 2025. The record tally of more than 10 000 submissions now sits on the desk of the Portuguese Environment Agency, whose decision on the project’s Environmental Impact Declaration is due in early 2026. Any approval would then move to the Direção-Geral de Energia e Geologia for licensing, creating an overlapping chain of authorities that campaigners say masks accountability.

In Parliament, the debate has broken party lines. The People-Animals-Nature party calls for a moratorium on mega-installations in sensitive landscapes; Communist deputies decry corporate speculation, while Socialist MPs press the Environment Minister to prove the process meets EU transparency directives. The government, eager to treble solar capacity to 20.4 GW by 2030, walks a tightrope between climate diplomacy in Brussels and rural disquiet at home.

Could the sun shine elsewhere? The search for less sensitive land

Technicians at the National Laboratory of Energy and Geology have spent two years mapping “areas of lower sensitivity” that meet solar-radiation thresholds without colliding with the Reserva Ecológica Nacional or Natura 2000. Early drafts—still confidential—highlight industrial estates near Setúbal, reservoir shorelines in the Alqueva basin and motorway margins south of Évora. The laboratory’s work dovetails with Brussels’ Renewable Energy Directive III, which urges member states to create Go-To Zones where licensing can be completed in under twelve months.

Portugal has also expanded tax credits for rooftop PV under the Portugal 2030 competitiveness grants and the Fundo Ambiental, although the clock is ticking: the reduced 6 % VAT on panels expires mid-2025. Critics argue that accelerating those decentralised incentives could meet climate goals with less conflict and fewer kilometres of Very High Voltage pylons scarring the interior.

What comes next

For now, Sophia’s fate rests on the Environment Agency’s ruling. If the project is rejected, it will mark a turning point in Portugal’s energy story, signalling that ecological restoration and large-scale renewables must co-exist under stricter parameters. If it proceeds, the facility will be operational within three years, instantly becoming the country’s largest solar asset and a beacon for global capital eyeing Iberia’s sunbelt.

Either outcome will shape how Portugal balances its commitments to carbon neutrality, rural cohesion and biodiversity. The spotlight on Beira Baixa has already triggered a national conversation about what should count as progress—and who gets to define it—long before the first pile is driven into the Gardunha soil.